11.2.22: Update on The Village at M-22
Since our last update on 9924 Ottawa, drywall has been completed and we are prepping for paint. This modified Lakeshore Loft has been a favorite to follow along with and we cannot wait to see the finished product!
Over at 9927 Ottawa siding has begun. On our last update we asked if anyone could guess the color of the siding going up, don't think anyone saw this one coming! Flooring is complete and kitchen cabinets are in. This home will be listed for sale soon!
9921 Ottawa
Left: Kitchen cabinets are going in.
Center: A view of the electric fireplace in the master suite.
Right: Master shower is tiled and features a sky light.
At 11539 S Crescent siding has begun and drywall has finished. Next up? Paint!

If you remember from our last 9918 Ottawa update, this home was constructed with Superior Walls. We've finished siding on the home and you wouldn't be able to tell it has concrete walls!