3.15.23 Update on The Village at M-22


CRESCENT DRIVE

Walls are poured on lots 7, 43, 44.

 

Framing has begun on lot 41.

 

Backfill is finishing up on lot 42 and next up will be framing.

 

Lot 1 flooring is complete, cabinets are installed, and tile is finished in the master shower!

 

OTTAWA DRIVE

Lot 1 is finishing up with the final touches.


 

Lot 7 is being painted, cabinets, countertops and tile have gone in.

 

AND finally, lot 3 is framed, rough HVAC and plumbing are complete and the electrician has begun his work.