6.2.23 Update on The Village at M-22

Join our mailing list to receive additional blog posts from Cornerstone Homes TC!


CRESCENT DRIVE

LOT 41

Lot 41 is primed, flooring starts next week and siding is going up on the outside.

LOT 42

Lot 42 insulation is wrapping up with drywall starting next.

LOT 43 & 44

Rough mechanical, electrical and plumbing are in the works. Septic tanks are being put in and final grades are in the works.

LOT 7

Trusses are set to be delivered next week.

LOT 1

Painters are doing what they do best.


OTTAWA DRIVE

LOT 3

Kitchen cabinets, exterior stonework and decks have been installed.